Rain for Rent Deploys Custom Containment Solution for San Francisco-Oakland Bay Bridge Project

Rain for Rent, a leading provider of temporary liquid handling solutions, tackles unique liquid challenges every day. However, it’s not every day the engineering team is required to design and deploy a custom containment solution 175 feet in the air above the San Francisco Bay on what will be the largest self-anchored suspension bridge in the world.

Hampered by delays since the project began in 2002, the San Francisco-Oakland Bay Bridge is undergoing a seismic retrofit to bring it in line with transportation safety standards after it suffered significant damage in the 1989 Loma Prieta earthquake.

In preparation for a complex bolt repair that required drilling into the concrete structure, the bridge contractor needed to find a way to safely disperse the water necessary for cooling during the drilling process. Unable to release this water into the Bay because of its high pH levels and sediment content, the contractor needed a liquid handling partner with the resources to capture and transport the water from this confined and uniquely positioned jobsite. With the clock ticking on a proposed late 2013 opening date, the job had to be done fast.

An urgent call brought Rain for Rent’s local engineering team to the site to assess the job requirements. “We were told there was zero margin for error,” said Kyle Van Fleet, Rain for Rent project engineer. “Every drop of water had to be captured, contained and diverted off the bridge for transportation, and once the drilling started, stopping was not an option.” Drawing on its breadth of engineering experience and careful calculations, Rain for Rent quickly confirmed that the team could handle the job for all potential contingencies.

After constructing a steel gutter to capture the water under the drilling site, Rain for Rent ran a vertical pipe down 160 feet to direct the water into tanks placed on the floating pier end caps below. For additional protection against leakage, Spillguards – one-piece temporary containment berms – were installed under the tanks. Upon project completion, the water will be pumped from the tanks on the bridge to a set of tanks on a barge for transportation to the Port of Oakland for treatment and sanitary disposal.

“Not only did we deliver a watertight solution in a tight jobsite configuration, but we also enabled the contractor to pass the scrutiny of every possible regulatory hurdle,” said Tony De Bellis, Branch Manager, Rain for Rent. “What’s different about Rain for Rent is that we don’t just do the job we were contracted to do, we bring our seasoned engineering professionals on site to give constructive advice and input for the best possible project outcome.”

Source: http://www.rainforrent.com/

Tell Us What You Think

Do you have a review, update or anything you would like to add to this news story?

Leave your feedback
Your comment type
Submit

While we only use edited and approved content for Azthena answers, it may on occasions provide incorrect responses. Please confirm any data provided with the related suppliers or authors. We do not provide medical advice, if you search for medical information you must always consult a medical professional before acting on any information provided.

Your questions, but not your email details will be shared with OpenAI and retained for 30 days in accordance with their privacy principles.

Please do not ask questions that use sensitive or confidential information.

Read the full Terms & Conditions.